Verified project evidence
Commercial Building Case Studies
Explore documented commercial HVAC, central plant optimization, building automation and critical-facility projects. Each HTML case study identifies the project scope, preserves the original PDF as a download and qualifies historic or client-reported outcomes.
Strongest measurable outcomes
Featured case studies
Energy solutions · Atlantic City, NJ
Pepco Central Plant Optimization
5,370,000 kWh in reported electric savings during a defined 2013–2014 measurement period, with a nearly 25% operating-efficiency improvement reported in the source.
Mechanical services · Mount Laurel, NJ
NFL Films Chiller Upgrade
Two 450-ton replacement chillers, improved equipment redundancy and a reported 10–12% reduction in monthly electricity consumption.
More documented projects
More case studies
Energy solutions · Atlantic City, NJ
Pepco Data Center Upgrade
Precision cooling, redundant power, passive air distribution and integrated monitoring for a critical data center.
Energy solutions · Bryn Mawr, PA
Bryn Mawr College Controls Modernization
A five-year campus controls modernization that retained about 3,000 existing control points across 50 buildings.
Mechanical services · Education
Education Facility Indoor Air Quality
Diagnosis and correction of humidity and short-cycling issues, followed by building automation and maintenance support.
How results are presented
Project figures on these pages are tied to the original Tustin Group case-study PDFs. Historic, forecast or client-reported outcomes are labeled as such, and measurement periods are retained where the source provides them. Results for one facility are not guarantees for another.
Discuss your facility goals
Talk with The Tustin Group about commercial HVAC, energy management, building automation, fire protection, water management or commercial plumbing needs.